简体中文界面。帖子、指南及政策正文保留原文;未对原文作自动翻译。

the hours are in, the fixture still isn't

RobinBarnes0599 · 2025年10月21日 22:45 UTC

已关闭
RO
RobinBarnes0599
I included our staff time in this UR5e block-loading estimate. Learned that lesson. Fixture cost still unknown, and my colleague wants to know what a pilot buys us before agreeing to one.

18 条回复

AN
AnnaCarter1025

What uncertainty can the pilot answer without the final fixture? If it is whether the molded block can be located consistently, name that explicitly rather than presenting the trial as a production demonstration.

16
IS
IsaacBell0694

Put a spending limit beside that question. A pilot can consume its budget perfectly well while everyone agrees the result is interesting. There needs to be a decision at the end.

16
AN
AnilAbbott0027

And don't count a hand-prepared tray as free. You can use one to investigate a grip, but it won't settle what the complete loading job costs.

20
RO
RobinBarnes0599

Anna, locating the blocks is the uncertainty. Some sit differently in the existing manual holder. Anil, tray preparation is timed; I'm not claiming we have automated that.

23
WI
WillChan1096

We spent a modest amount on a holder study before choosing the handling equipment. It stopped us asking the arm supplier to cure a part-location problem. Would a bench study answer this before you need the UR5e present?

14
AN
AnilAbbott0027

Will's right to ask. If the block won't sit repeatably in the holder by hand, borrowing a robot can make a simple investigation much harder to arrange.

21
AN
AnnaCarter1025

It depends what Robin needs to learn. Hand seating is a useful first comparison, but it may conceal an awkward approach or extra manipulation that the proposed transfer cannot reproduce.

-2
IS
IsaacBell0694

Anna, that sounds like two decisions, not a reason to combine the costs. First find out whether the holder needs work. Then decide whether a handling trial is worth funding.

5
RO
RobinBarnes0599

Two decisions suits us. We can use identified production blocks for a capped holder study. The handling trial stays unapproved until that result and a fixture estimate exist.

10
WI
WillChan1096

Include the ones the operator finds awkward, Robin. On our study the convenient sample was also the only one the designer had handled. That did not make it a useful selection.

5
AN
AnnaCarter1025

Will, yes, and capture what makes them awkward in the operator's words before translating it into measurements. A small twist or an extra push can disappear from a tidy seating description.

23
AN
AnilAbbott0027

Who owns the holder study? Please don't make it Robin's unofficial evening project and then call the labour allowance settled.

4
RO
RobinBarnes0599

Toolmaker owns it, Anil. Booked hours, including my observation time. Operator says one moulding batch catches at the entry, so that batch is in Will's sample group.

20
IS
IsaacBell0694

How does your colleague want the result presented? Buying a fixture and abandoning the idea should both be possible answers, not only different sizes of the next trial.

5
RO
RobinBarnes0599

He wants the proposed holder changes, their cost, and the work still left to a person. Fair request. Thanks Will for the bench-study suggestion; it reduced the immediate ask considerably.

10
AN
AnnaCarter1025

Robin, has the catching been observed by the toolmaker yet? The batch link is worth following, but I would not describe it as a molding cause until the parts and holder have been compared.

7
WI
WillChan1096

Anna's caution matters. Our awkward pieces exposed a damaged contact in the holder, not a reason to reject the incoming batch. Same complaint, different bill.

21
RO
RobinBarnes0599

Observed, not explained yet, Anna. Study still running within the agreed hours. No UR5e order, and no claim that the holder modification is obvious.

16

讨论已关闭

此讨论已连续六个月没有活动,现已关闭新回复。 最后活动: .