the ur5e study still needs somebody to make its fixtures

JackAli0254 · 2025年12月18日 15:59 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

JA
JackAli0254
I priced a spacer-unloading pilot without pricing my colleague's fixture work. What bounded study would let us compare the complete task before either of us commits to building it?

3 条回复

TH
TheoBrooks0845

Define its questions, deliverables, staff allowance and stop point before pricing any physical pilot.

6分
JA
JackAli0254

We have agreed to compare preparation through the finished tray, including interruptions. The designer is pricing options and a review, not production tooling. My colleague's time allowance still needs agreement.

5分
TH
TheoBrooks0845

Keep that allowance unresolved in the total. Agreeing the task doesn't make his time free.

21分

讨论已关闭

此讨论已连续六个月没有活动,现已关闭新回复。 最后活动: .