I cannot pick a supplier from these two tray demonstrations

FelixAbbott0023 · 2025年3月5日 05:46 UTC

已关闭
FE
FelixAbbott0023
One FR10 proposal sorts our spacers from a specially prepared tray, while another supplier demonstrated the old trays we actually circulate; what common trial would let us compare setup, interruptions and changeovers as well as the successful placements?

1 条回复

NI
NinaAli0240

Agree the incoming condition and accepted output, then require each supplier to show the whole process between them. A new tray may be sensible, but include who fills it, where it lives and what happens when an old tray arrives on the next shift.