Our FR10 bracket proposal inherits a correction allowance from old sheets, but the sketch beside the released height names a face which is not the drawing datum; before pricing a new fixture I want to know what was actually measured
Had a handover where the inspector's little sketch was of the part upside down. The numbers were right, the explanation wasn't. Can the person who took these readings show the setup with a retained bracket? Don't start by declaring the whole batch wrong.
A reconstruction may explain it. It can't recreate readings nobody recorded. Ask which parts are still identifiable before spending hours arguing over the handwriting.
Inspector demonstrated the correct datum setup on an identified retained bracket; copied sketch belongs to an earlier component, and quality has withdrawn it from the proposal
Make the first released check happen where the work happens. If the bracket reaches the correction bench first, you'll collect another perfectly tidy set of answers to the wrong question.
Include ordinary brackets that don't need correction too. Last time we followed only the rejects, the resulting allowance made every job look worse than it was.