Neither meaning should win by accident. Give them different names and ask both suppliers to write the event behind each one. I'd take the word ready out of that discussion until they stop nodding at different things.
简体中文界面。帖子、指南及政策正文保留原文;未对原文作自动翻译。
Can't finish the FR5 interface while ready has two meanings
IsabelBarnes0561 · 2025年8月13日 23:01 UTC
20 条回复
I tried received and loading available. Machine supplier says received happens immediately, loading available can follow later. That is already clearer than their timing diagram.
6分Good, now ask the integrator which event its sequence needs at each step. Don't simply rename the existing wire and leave the old assumption in the program.
11分Include the operator display in that agreement. Received should be visible while it waits. Otherwise the person at the screen sees nothing happen and tries another request. Seen that turn a clear sequence into a confusing shift report
12分Is loading available only ordinary sequence status, with the actual safety permissions handled separately?
19分Yes, Sofia. Safety functions are separate. The ordinary interface tells the sequence where the machine job has got to. Screen currently says ready for both meanings too.
5分Then put that distinction in the names, including on the screen.
18分Our diagram was lovely until someone asked what happened when a request was cancelled. Who owns that on yours? Don't leave it to whoever gets bored of waiting first.
7分Nina's cancellation question is worth a separate example in the walkthrough. Which side knows whether any loading has started by the time cancellation is requested?
15分Not agreed. Machine supplier calls cancel a new command. Integrator calls it clearing request. I think we've found the next argument.
4分I'd describe what the caller wants to happen instead of choosing either implementation first. Withdrawing an unaccepted request and dealing with a job already under way can need different handling.
12分Name the person who deals with an uncertain job too. The screen can show waiting all it likes, but someone needs authority to investigate when neither side can say whether the spacer moved
12分Controls lead is taking ownership. We've split not yet accepted from accepted and waiting. Cancel after acceptance stays unresolved while both suppliers agree the handling.
12分Can the operator read the request details while that uncertainty remains?
20分Please don't give them a clear button that also sends another request. Ours did, briefly. Quite a lot hidden behind one small word.
13分Sofia and Nina are pointing at different controls: looking at the job and changing its state. Have the screen draft show both, with the state-changing actions agreed by controls.
22分Screen draft now lets them view the job without changing it. Nina, no combined clear-and-request button. Bruno, thanks for separating the events first. That got both suppliers talking.
4分Did they agree what happens after a connection loss as well? You could have the new names right and still disagree about an old request when the link comes back.
4分Connection-loss cases added to the review, no agreement yet. Normal sequence wording is signed by both suppliers. I'm keeping recovery marked unfinished.
13分Keep that unfinished bit on the cover sheet. People love forwarding only the page with two signatures.