A second bracket proposal leaves straightening outside the quoted cycle

WillBarnes0574 · 2025年7月1日 02:01 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

WI
WillBarnes0574
I'm reviewing a separate UR5e bracket proposal now. Its estimate ends at release, while the historical route continues through straightening and final inspection. The correction rate is missing, so the complete cycle comparison is still open.

7 条回复

LE
LeoCarter0971

We found an old process summary reporting only the accepted output, which concealed the rework. Can you link the final inspection sheets to the same individual brackets measured before straightening, rather than compare two batch totals?

10分
WI
WillBarnes0574

Some individual marks survive, but the before-straightening sheet is incomplete. We cannot calculate a reliable rate for the whole run from what is there.

5分
BR
BrunoAli0191

Our UR5e quote had a similar route gap. We asked for a current-part trial with fabrication and quality involved. Still worth finding what the old bench work did, even if its rate can't be recovered.

9分
LE
LeoCarter0971

Do the traceable old cases use the current component revisions? I would establish that before carrying their correction method into the new requirements.

2分
WI
WillBarnes0574

No, assembly revision B rather than current D. Fabrication is comparing the gusset change and defining a current trial. I have left correction as an unresolved estimate item.

8分
BR
BrunoAli0191

Put that unresolved item in the layout brief too. Someone can leave the cost blank and still draw away the space needed to do the work.

11分
LE
LeoCarter0971

Did the current trial produce any paired results yet? Interested whether the revision comparison changed which measurements the team wanted.

12分

讨论已关闭

此讨论已连续六个月没有活动,现已关闭新回复。 最后活动: .