Fairino FR5: How do I get both suppliers to define ready?

DavidBarnes0606 · 2026年4月18日 02:37 UTC

回复讨论
DA
DavidBarnes0606
I'm writing up documenting a machine-tending interface, with Fairino FR5 handling a machined bush in a planned enclosed machining cell. The machine supplier says 'ready' means request received. Our integrator means loading area available. We're still planning, but this is getting circular. How do I get one definition both teams accept?

12 条回复

CH
ChloeBrooks0831

@DavidBarnes0606 Can you put the two definitions beside each other, with the sender and receiving system named? Start with that single disputed transition.

10
DA
DavidBarnes0606

Yes. Both documents show machine to robot, but one describes accepting a request and the other says the area is available. Same arrow, different event

15
CH
ChloeBrooks0831

@DavidBarnes0606 Make separate rows for request received and resulting state confirmed, with an owner for each. That should clear up the normal handover on paper.

11
CA
CallumAllen0273

@ChloeBrooks0831 That table could still lose track of the part. Separating the signal meanings doesn't establish who holds it through the handover.

4
CH
ChloeBrooks0831

You're right; I overstated what those rows settle. Add known part location and the point where custody becomes uncertain. Signal definitions are only the start.

18
DA
DavidBarnes0606

The sequence drawing has a transfer box but no custody note inside it. Neither document says who reconciles that state after an interruption

13
JA
JackCarter1037

On another tending project, we moved a paper part token between boxes. It felt silly until both teams put it in different places.

9
JO
JoAli0244

Does the token need a box for unknown, then?

25
CH
ChloeBrooks0831
回复 JoAli0244

@JoAli0244 Yes. Unknown is a legitimate state to document. Give it an authorised recovery owner rather than drawing an arrow straight back into normal operation.

20
DA
DavidBarnes0606

Would you put recovery ownership in this table or a separate procedure? I'm trying to keep it readable without hiding the awkward bit again

7
CH
ChloeBrooks0831

Name the responsible role in the table and reference the procedure there. The detailed instructions can live separately if the link and revision are explicit.

7
CA
CallumAllen0273

Check they name an actual responsible role. 'Other system' would just put the original disagreement into a tidier document.

11