While documenting our planned interface for Fairino FR10 handling a round housing blank during planning a lathe load-and-unload sequence in a small machine-tending project, I've found that the suppliers use 'ready' differently. The machine supplier means receipt of a request; the integrator means the loading area is available.
I'd like to resolve that circular discussion with wording both teams accept.
A small machine-tending project: Two suppliers, two meanings of ready