our bracket spreadsheet quietly deleted the press operation

BenAdams0109 · 2025年8月31日 22:33 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

BE
BenAdams0109
I'm checking the FR10 bracket estimate. The old route has a press operation between welding and accepted dimensions. The new spreadsheet removed it and kept the old acceptance figures. Nobody can explain that leap, but everybody likes the resulting cycle time.

9 条回复

HA
HassanArcher0356

Restore the correction and inspection as unresolved work in the estimate until a current-part trial establishes which operations remain necessary.

15分
BE
BenAdams0109

Estimator has put them back as open lines. Fabrication says the press was used on some batches, not all. No batch-by-batch count yet.

20分
HA
HassanArcher0356

Ask whether the old route cards identify those batches; an average based on memory would give the spreadsheet another attractive number with weak foundations.

11分
JU
JuliaAbbott0065

Do the final figures all use the same drawing revision? Could be another difference hidden in that spreadsheet.

14分
BE
BenAdams0109

Julia, no. Two revisions are mixed. I've separated them and asked quality which measurements changed between the drawings.

25分
BE
BenAdams0109

Route cards identify press use for part of the period. Earlier cards are missing. We can describe that subset, not claim an overall correction rate.

8分
HA
HassanArcher0356

Keep the missing period visible alongside any quoted rate, and have the trial cover the current component and fixture proposal rather than reproducing whichever old batch is easiest to document.

7分
BE
BenAdams0109

Trial scope is with welding and quality now. Current revision only, with individual pieces followed through released measurement and any correction. No results yet. At least the estimate no longer pretends the press was decorative.

10分
JU
JuliaAbbott0065

Who keeps the sample IDs attached when the brackets move to the press? Worth settling before the trial starts.

20分