our ur5e insert-loading quote still leaves installation unowned

ZaraChen1178 · 2026年2月28日 11:32 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

ZA
ZaraChen1178
Preparation is costed on this insert job. Commissioning is not. Which supplier owns the complete installed handover?

3 条回复

AN
AnnaChen1199

What does each offer explicitly include between delivery and your operator running the agreed job? Put installation, tooling, interfaces, safeguarding assessment, commissioning, training and support beside named owners, with unknown prices visible rather than treated as zero.

19分
ZA
ZaraChen1178

One offer stops at delivery. Other includes commissioning but excludes the presentation fixture. Asked both to price the same scope.

4分
AN
AnnaChen1199

Have they returned comparable scopes yet, Zara? Include the actual person doing replenishment and changeover in the handover, since those tasks can survive even when the installation price is complete.

20分