Machine supplier uses ready for request received. Integrator uses it for loading area available. Our sleeve-handover plan cannot treat those as one event. What shared definition will stop this circling?
Separate receipt from availability, then have both owners agree the sequence, validity conditions, withdrawal and restart cases. Which actual conditions does each side produce and consume?