How should I check the loaded gripper through this narrow opening?

JuliaAllen0326 · 2025年4月10日 10:29 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

JU
JuliaAllen0326
I have another FR5 access proposal to review, this time handling brass blanks beside a mill with a partly obstructed door opening. The sketch omits the complete gripper. What minimum geometry should I request before paying for a detailed motion study?

14 条回复

AN
AnnaAbbott0068

Start with the whole tool assembly and the brass part in it, because a finger drawing without its body and fittings leaves the expensive collision candidates invisible.

17分
JU
JuliaAllen0326

The supplier has only sent finger dimensions so far. The body is shown as a centre point. I have requested the assembly and measured door position.

14分
AN
AnnaAbbott0068

Open fingers as well. They need somewhere to go.

12分
JU
JuliaAllen0326

Added. The mill owner also points out that the door stops against an external bracket before reaching the nominal fully open position.

21分
AN
AnnaAbbott0068

Have you got that bracket measured yet? That's likely to matter more than another catalogue picture.

8分
MI
MiaAli0209

Please let the person who changes the fixture see the stand position. We always seem to leave room for the robot and then remember that somebody has to carry the tooling in. Usually while holding a surprisingly heavy box.

10分
JU
JuliaAllen0326

The bracket is measured. Our setter reviewed the stand position and wants it farther from the machine for fixture access, which gives the motion reviewer two candidate positions.

17分
GR
GraceBarnes0581

We marked our proposed base on the floor and immediately found the trolley couldn't turn, would a quick walk-through help you compare those two spots before paying for both studies?

11分
JU
JuliaAllen0326

It did. The closer position prevents the fixture trolley reaching its usual loading point. We have dropped that candidate and sent the farther position for review.

17分
EL
EllaBrooks0816

Check the service panels while you're there, I mentioned our hose-fitting access in another thread because it was exactly the thing nobody looked at until the stand got in the way.

1分
AN
AnnaAbbott0068

Has the complete tool arrived on the drawing yet?

7分
JU
JuliaAllen0326

Yes, including the open state and fittings. The initial study found a candidate route but requires confirmation of the hose routing. Service access is clear at the proposed position.

20分
AN
AnnaAbbott0068

Get the hose supplier or toolmaker to settle that routing, then have the reviewer rerun the candidate with it included.

10分
GR
GraceBarnes0581

Who'll keep the final assembly drawing with the cell? Ours was in the toolmaker's email until a replacement fitting sent us looking for it.

13分