Why are we still calling two different FR5 handover states ready?

DavidChan1128 · 2025年11月23日 20:19 UTC

已关闭
DA
DavidChan1128
I have asked for the called routines and the permission definitions this time. We are planning an FR5 sleeve-blank handover, not repairing the teaching example I mentioned earlier. The machine supplier has sent a definition. Its ready response acknowledges our request. Our integrator has written the same word beside permission to enter the loading area. Both have now read the other's page and still say there is no disagreement. How do I get this settled before it becomes a lesson somebody has to unlearn?

13 条回复

WI
WillAdams0139

Put the two meanings on separate lines. Ask each team what changes the state and what the receiver may do with it, without using ready in the answer.

7
SO
SofiaBrooks0804

We inherited a screen where ready meant the previous job was accepted. The machine was still occupied. The operator caught it before anyone wrote the training notes, but it cost another handover visit.

12
DA
DavidChan1128

Will, I have split the lines. Sofia, ours has no screen yet. I want to keep this wording out of it rather than correct it later.

25
TH
TheoBarnes0584

Good. But has anyone actually said where the loading permission comes from? Two better labels still leave that job unassigned.

4
VI
VictorBell0620

And don't make the eventual operator guess which team's version of ready the screen is showing.

22
DA
DavidChan1128

Theo, the integrator says it will derive the loading permission from machine states. It has not listed those states yet. The machine supplier only owns the acknowledgement on its page.

12
SO
SofiaBrooks0804

Then I would put the missing state list in the integrator's work. Copying the acknowledgement into its drawing is easy. Explaining what happens when the request is received but loading is unavailable takes more effort.

14
WI
WillAdams0139

Try that unavailable example in the joint review, David. It gives both teams something concrete to answer instead of another round of vocabulary.

5
TH
TheoBarnes0584

Who is checking the safety-related permissions separately? I wouldn't let this ordinary request acknowledgement wander into that role by accident.

23
DA
DavidChan1128

The cell integrator owns that assessment, Theo. I have asked it to distinguish those conditions in the interface review too. The unavailable example is on the agenda.

15
VI
VictorBell0620

Can maintenance explain the proposed states back to them at that review, rather than just watch both suppliers nod?

14
DA
DavidChan1128

Maintenance found the gap in the review. The request can be acknowledged while loading remains unavailable, and both suppliers have now said that explicitly. We have separate draft names. Permission conditions and loss-of-permission behaviour still need agreement.

8
WI
WillAdams0139

Useful progress. Leave those last two items visibly unfinished in the teaching material; the clearer names will otherwise make the interface look more settled than it is.

19