I cannot compare FR10 packing quotes with customer fixtures left blank

TheoBrown0932 · 2026年3月12日 16:35 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

TH
TheoBrown0932
Our boxed-kit packing proposals both assign presentation fixtures to us. One includes fixture design; the other does not say. Guarding and training are separate allowances. I need to know which costs are firm before the lower robot price decides this comparison for us.

1 条回复

AN
AnikaBennett0769

Ask who designs and who makes each fixture, then price your own work against that split; an empty supplier line is not evidence that your toolroom can absorb it