the FR5 price survived; my packing-cell budget did not

ChrisChambers · 2026年8月15日 12:44 UTC

回复讨论
CH
ChrisChambers
Need a whole packing-tray cell comparison. FR5 quote looked manageable; presentation fixtures, guarding and training keep appearing afterwards. How do I show the unknown costs honestly?

16 条回复

SA
SaraAbbott0026

Separate priced scope, allowances and exclusions. An excluded fixture is still something you must fund, even if it is absent from the supplier total.

11
NA
NadiaCarter0987

What end condition are the proposals meant to deliver? Write that consistently first, including carton presentation and handover. Otherwise you may be comparing different jobs rather than different suppliers.

20
JA
JasperChan1073

Who handles carton changeovers afterwards? Include that work before the inexpensive hardware becomes an expensive standing appointment.

21
CH
ChrisChambers

Current quotes assume different presentation. One expects our own nest. Training is a day in one offer, unspecified in the other.

17
RE
ReeceBell0645

Does either proposal assign responsibility for safeguarding assessment and implementation, or is guarding just an allowance with no defined scope?

11
SA
SaraAbbott0026

Ask for matched scope, not a larger discount. Even the smaller offer cannot be ranked until those omissions are priced or bounded.

20
NA
NadiaCarter0987

Training also needs an agreed outcome. A day may be enough for one role and inadequate for another; list operator changeover, maintenance information and exception escalation rather than treating attendance as the deliverable.

23
CH
ChrisChambers

Sent a common scope. Safeguarding owner now named, assessment cost included; implementation still an allowance. Internal nest work has a quoted estimate from tooling.

11
JA
JasperChan1073

Was tooling given the actual carton variation? A fixture estimate for one ideal sample may leave the expensive bits outside again.

3
CH
ChrisChambers

Yes, same retained carton set went with both supplier enquiries and our tooling estimate. Variant changes outside that set are explicitly separate.

23
SA
SaraAbbott0026

Now compare the bounded ranges against your budget. You need not wait for every detail to learn that even the lower bound is unaffordable.

14
RE
ReeceBell0645

I would be careful with that lower bound. Have you included customer labour, or only external invoices?

24
CH
ChrisChambers

Included customer labour. Revised proposals came back; both lower bounds exceed what we can spend on this packing job. Not by an amount another optimistic blank row will solve.

10
JA
JasperChan1073

Then tell the people reserving installation time now, even before the final purchasing decision. Don't leave them planning around the original arm-only number.

24
CH
ChrisChambers

Purchase cancelled for this job. Manager agreed the complete estimate does not fit our budget, and installation time is released. Keeping the scope comparison for any future proposal, not buying the arm to force a decision later.

23
NA
NadiaCarter0987

Keep the assumptions dated with it. A future comparison can start from that record, but should not inherit old costs or carton conditions without checking them.

14