Separating fit-up, restraint and final inspection

OliverBarnes0537 · 2026年6月7日 23:40 UTC

回复讨论
OL
OliverBarnes0537
We're planning reviewing fixtures for welded mounting brackets with Fairino FR5 on a steel gusseted bracket assembly in a precision fabrication quality department. Our old inspection notes say it looks aligned while restrained, then falls outside the drawing requirement after release. I want to untangle fit-up, fixture location and final inspection before our new cell inherits an unexplained correction routine. This is a records review, not live welding adjustment.

3 条回复

NA
NaomiChan1115

Does the inspection procedure define the released condition and reference supports? Check that alongside whether each old measurement says how the assembly was held.

11
OL
OliverBarnes0537

The sheets mix clamped checks and released measurements. Some don't say which. The drawing has the dimension, but our procedure leaves the support condition vague.

3
NA
NaomiChan1115

Have quality and the drawing owner define the acceptance condition. Group the old results by known measurement state; that should make them comparable.