Which bracket readings can justify another clamp in our UR5e fixture?

AmyAbbott0032 · 2025年9月4日 08:44 UTC

已关闭
AM
AmyAbbott0032
Our UR5e bracket proposal adds a clamp because the old parts needed correction after release. I've found final accepted figures, but none from before correction. I want to see what actually went wrong before buying more restraint.

2 条回复

BR
BrunoChan1061

Ask fabrication and quality to identify the feature being corrected and its released checking method, then keep that correction work in the estimate until a current-part trial gives you something firmer than the old final figures.

18
AM
AmyAbbott0032

Fabrication identified the upright angle. Quality found the released check, but no untouched samples or pre-correction readings. We're asking for a fresh sample run; extra clamp stays a proposal, not an order.

21