I sat with our bracket inspector to understand an old final-pass sheet. The bracket had been checked after release, sent for correction, then checked again. Only the last result reached the sheet used in our FR10 proposal. The inspector remembered the extra trip because she had to find someone available to do it. Nobody timed that wait or the correction. I can see why the final result was recorded. I cannot see why the estimate treats it as the result directly out of the fixture. I need a comparison that includes the work between those two points.

18 条回复

JU
JuliaBaker0500
回复 JamesBlair

Start with what sends it for correction. The person doing the next trial needs a clear released check and decision, not a box called rework that everybody fills differently after the batch.

14
JA
JamesBlair

The inspector uses the released bracket against the drawing requirement. The old estimate combined that check with final acceptance under one inspection allowance. It did not include a correction operation.

21
LI
LiamBell0664
回复 JamesBlair

Then it is missing work, not merely using an optimistic time.

18
AM
AmaraAdams0165
回复 JamesBlair

Who actually does the correction when your usual person is busy? That sounds like a resource constraint hiding inside the quality route.

7
AN
AnnaCarter1025
回复 JamesBlair

Keep the same bracket identity through both checks. I mean the actual piece, not just its batch, because the extent of correction may vary and a final pass alone won't describe that variation.

3
MA
MarkBailey

A simple traveller with the bracket would help keep those entries together.

17
HA
HazelBell0658
回复 MarkBailey

Mark, provided someone owns completing it. We had lovely blank travellers once; everyone thought the next bench added the times

16
JA
JamesBlair

Amara, a fabrication technician does it, and availability varies with other work. Anna, the proposed trial will keep individual bracket identities. Mark and Hazel, we have assigned the entries at each handover rather than one person completing everything later.

15
MI
MinaBrown0946
回复 JamesBlair

Will the trial use the same incoming parts and fixture revision as the FR10 proposal, or are those changing too?

12
ZA
ZaraBaker0482

Mina's question matters. Paired readings can describe the present process well while still being a poor prediction of a different fixture or fit-up. Keep that distinction in the estimate when the trial scope is agreed.

12
RE
ReeceArcher0384

Could the old result still be useful background? No need to throw the inspector's work away.

12
JU
JuliaBaker0500

Yes, Reece. It tells James there was a correction route worth investigating. It just doesn't supply the missing time or prove the proposed fixture will need the same amount.

12
JA
JamesBlair

Mina, current incoming parts are the same revision, but the proposed fixture changes two locating contacts. We will study the existing process first and keep the proposed-fixture trial separate. Thank you Julia; that describes the useful limit of the old sheet.

6
AM
AmaraAdams0165
回复 JamesBlair

Then keep the technician's waiting time separate from the correction work. Otherwise somebody may try to improve the fixture to solve a queue, or improve the staffing and claim the bracket stopped distorting.

18
HA
HazelBell0658

Amara, and count the walking between benches somewhere too. It can be sensible work, but it doesn't vanish because neither machine is doing it

22
AN
AnnaCarter1025
回复 JamesBlair

Have the inspector and technician tried one completed example of the traveller together? That may expose a handover neither thinks belongs to them before the comparison starts.

21
JA
JamesBlair

They tried an example and found the return check had no owner after correction. That is assigned now. The study has not run, and the FR10 estimate carries the correction work as unresolved rather than zero.

20
LI
LiamBell0664
回复 JamesBlair

Will purchasing wait for that study before comparing the totals?

8