I cannot choose an FR10 proposal with three empty cost lines

WillBennett0748 · 2026年3月7日 13:35 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

WI
WillBennett0748
The small-carton filling quote looked reasonable when it was an FR10 and a gripper, and now I have presentation fixtures, guarding and training in separate conversations with no combined price. One supplier says training is included but means an introduction at its premises. We need people able to run the agreed job after handover. I am trying to make a fair comparison without pretending our internal work is free or asking a supplier to price a fixture we have not defined. What would you settle first?

14 条回复

YA
YasminBell0615

Who defines the fixture? That seems to be blocking the rest.

23分
WI
WillBennett0748

Our toolroom and the integrator together, but neither had allowed time for that design work in the quoted figures; I have asked them to price a defined study before the production fixture.

10分
GR
GraceChen1190

Did the study price arrive?

11分
WI
WillBennett0748

Yes, with a deliverable covering presentation and access options using our carton samples. We approved that stage. The arm order is still separate, and the complete fixture cost remains unknown.

2分
CH
ChloeAbbott0048

Your training point deserves its own line too. An introduction can be useful, but who teaches the actual changeover and interrupted-job decisions? I've seen a course certificate arrive long before anyone knew who could answer a production question

19分
AL
AlexAdams0124

Does either proposal include support after that job-specific handover?

12分
WI
WillBennett0748

Chloe, our training lead has written the job-specific scope. Alex, one supplier includes a defined support period for its application, the other only hardware enquiries. That difference was invisible in the original totals.

6分
YA
YasminBell0615

Are you comparing those as different offers, or asking for matching support?

9分
GR
GraceChen1190

Different can be acceptable. Invisible is the expensive part

12分
CH
ChloeAbbott0048

Grace, yes, but somebody must cover the gap if they pick hardware-only support. Will, does your own team actually want to maintain that application, or is purchasing volunteering them?

9分
WI
WillBennett0748

They do not have capacity to own it. We asked the hardware-only supplier to quote application support too; they declined, so that proposal is no longer a complete alternative for us.

23分
AL
AlexAdams0124

And guarding remains in the remaining supplier's scope?

22分
WI
WillBennett0748

Included in the study's integration scope, with final cost to follow the assessed layout. We can choose who does the study now, but the final cell purchase still depends on the fixture and guarding total.

8分
YA
YasminBell0615

That sounds like a decision you can actually make.

23分