I cannot compare our UR5e carton-filling proposals yet. One prices the presentation fixtures and operator training; the other leaves both as customer provision. Guarding is still being scoped. How do I show those gaps without making a guessed allowance look like a supplier commitment?
Carton-filling estimate with unpriced preparation work