our fr5 tool is complete on paper and owned by nobody

YasminCarter0963 · 2026年2月24日 10:53 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

YA
YasminCarter0963
I have asked for the full assembly this time: motor housing, extended fingers, adapter and fittings, with their positions. Both FR5 suppliers still answer with the housing mass. One says the fingers are the tooling company's responsibility; the tooling company says ask the robot supplier. Who is supposed to turn these bits into one assessed proposal before we buy it?

11 条回复

JO
JoAli0244

Who contracted to integrate the complete tool? Start with that responsibility, not another mass estimate.

25分
YA
YasminCarter0963
回复 JoAli0244

Nobody yet. These are quotations, and each leaves assembly integration outside its own scope. I have asked both to include a named owner and price that work before we compare them again.

20分
JO
JoAli0244

That missing scope is the purchase problem, then.

21分
AM
AmaraBarnes0600

Include which assembly revision that owner will assess, so the fingers eventually ordered and the spare adapter in stores don't belong to a different version of the successful proposal.

4分
YA
YasminCarter0963
回复 JoAli0244

One supplier has declined the combined work. The other has revised its offer with an integration engineer responsible for the complete arrangement, including the handling cases and applicable limits. The technical review is included in the offer, not completed yet.

7分
LI
LiamBrooks0838

Make sure the integration engineer gets the intended movement and release arrangement too. A complete component list still does not describe how the tool will be used beside the fixture.

-8分
JO
JoAli0244

Did that engineer find anything missing from your assembly information?

24分
YA
YasminCarter0963
回复 JoAli0244

Yes, the hose fittings were listed but their positions were not fixed. Our tooling owner has settled the route and supplied it with the loaded and open-tool arrangements. That was a useful question from the engineer, not another request to repeat the housing weight.

19分
AM
AmaraBarnes0600

Has the resulting assembly revision reached purchasing as well as the engineer, Yasmin?

18分
YA
YasminCarter0963

It has. The engineer completed the assessment for that revision and the stated handling cases; purchasing selected the revised offer with integration included. The first offer is out. Installation and commissioning still follow, but there is finally an owner for the assembly we are ordering.

17分
JO
JoAli0244

Good. Keep that responsibility in the order, not just the helpful email.

21分