The bracket passes after a correction nobody timed

GraceCarter1016 · 2025年11月16日 02:08 UTC

已关闭
GR
GraceCarter1016
Quality has defined our released-bracket check now. The FR5 estimate still uses final pass sheets that include unrecorded straightening. I can name the missing operation; I still can't price its frequency.

19 条回复

DA
DavidBrown0954

Do the operators recognise which parts needed straightening, or has everything been mixed back into the finished batch?

13
GR
GraceCarter1016

Mixed finished batch. Two operators remember the difficult ones, not a count.

18
MA
MayaAbbott0040

Don't make a percentage from the memorable ones. Ours were memorable precisely because they were awkward.

11
JA
JamieBarnes0556

Is there an existing correction entry on the route, even if no time was recorded?

0
GR
GraceCarter1016

Yes. One tick for the batch after the bench work. No individual-part entries.

18
NO
NoraChan1105

Our revised fixture plan needed current-part observations for that reason. Could your next ordinary batch distinguish released checks from later correction, with the same part identities through both?

14
DA
DavidBrown0954

And who puts the tick in, Grace? The person doing correction or somebody closing the paperwork afterwards?

9
MA
MayaAbbott0040

The batch tick at least tells you the operation wasn't imaginary. Keep it as history without asking it to reveal which brackets went through the vice.

19
GR
GraceCarter1016

Inspection closes the batch route, David. The operator does the correction. We've agreed a current batch with individual entries; the estimator knows the old tick can't supply a rate.

2
JA
JamieBarnes0556

Same drawing and acceptance method for that current batch as the proposed fixture review?

18
GR
GraceCarter1016

Drawing H. Released check to quality's current method. Fixture designer has both.

15
NO
NoraChan1105

Are incoming fit-up differences recorded too, Grace? I wouldn't want the new fixture blamed for a variation that was already there before the bracket was assembled.

6
MA
MayaAbbott0040

Nora, yes, but don't let the observation sheet grow until nobody fills it in. Ask the people doing the work which details they can reliably capture.

18
DA
DavidBrown0954

Could the operator and inspector try one blank sheet together before the batch starts? That should expose any field each thinks the other person completes.

8
GR
GraceCarter1016

They did. Correction start was owned by nobody. It now has a named recorder.

18
JA
JamieBarnes0556

Good catch before the trial. Does the entry distinguish active correction work from waiting for inspection?

22
NO
NoraChan1105

That split helped us explain cost without pretending the operator spent the whole interval correcting. The waiting still affected delivery, just for a different reason.

14
GR
GraceCarter1016

Yes, separate now. First current batch recorded; quality is checking the linked readings before we use the count.

16
DA
DavidBrown0954

Will you post whether the correction frequency was anything like the remembered problem batch? Curious how far the memories and the ordinary work diverged.

15