I cannot compare FR10 totals with the fixture cost left blank
JuliaChan1109 · 2026年4月9日 01:05 UTC
回复讨论Our FR10 carton-insert proposal prices the arm, but leaves presentation tooling, guarding and cover-shift training unpriced.
7 条回复
Are those items excluded, or included with prices still outstanding?
12分Guarding included but unpriced. Presentation tooling excluded. Training priced for one person only, with no covering-shift allowance.
12分Then compare named scopes first. The current totals describe different purchases.
11分Both suppliers now have the same scope sheet, including tooling ownership and the covering shift.
20分Who prices the excluded presentation tooling?
20分Our fixture designer is quoting it, with integration responsibility still to be agreed between the parties.
17分Leave that responsibility visible beside the cost. It affects support as well as purchase approval.