I cannot compare FR10 totals with the fixture cost left blank

JuliaChan1109 · 2026年4月9日 01:05 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

JU
JuliaChan1109
Our FR10 carton-insert proposal prices the arm, but leaves presentation tooling, guarding and cover-shift training unpriced.

7 条回复

CH
ChloeBrooks0831

Are those items excluded, or included with prices still outstanding?

12分
JU
JuliaChan1109

Guarding included but unpriced. Presentation tooling excluded. Training priced for one person only, with no covering-shift allowance.

12分
CH
ChloeBrooks0831

Then compare named scopes first. The current totals describe different purchases.

11分
JU
JuliaChan1109

Both suppliers now have the same scope sheet, including tooling ownership and the covering shift.

20分
CH
ChloeBrooks0831

Who prices the excluded presentation tooling?

20分
JU
JuliaChan1109

Our fixture designer is quoting it, with integration responsibility still to be agreed between the parties.

17分
CH
ChloeBrooks0831

Leave that responsibility visible beside the cost. It affects support as well as purchase approval.

4分