I cannot compare FR10 totals with the fixture cost left blank

JuliaChan1109 · 2026年4月9日 01:05 UTC

回复讨论
JU
JuliaChan1109
Our FR10 carton-insert proposal prices the arm, but leaves presentation tooling, guarding and cover-shift training unpriced.

7 条回复

CH
ChloeBrooks0831

Are those items excluded, or included with prices still outstanding?

12
JU
JuliaChan1109

Guarding included but unpriced. Presentation tooling excluded. Training priced for one person only, with no covering-shift allowance.

12
CH
ChloeBrooks0831

Then compare named scopes first. The current totals describe different purchases.

11
JU
JuliaChan1109

Both suppliers now have the same scope sheet, including tooling ownership and the covering shift.

20
CH
ChloeBrooks0831

Who prices the excluded presentation tooling?

20
JU
JuliaChan1109

Our fixture designer is quoting it, with integration responsibility still to be agreed between the parties.

17
CH
ChloeBrooks0831

Leave that responsibility visible beside the cost. It affects support as well as purchase approval.

4