Which bracket measurement happened before the correction?

OliverCarter0972 · 2026年8月15日 05:36 UTC

回复讨论
OL
OliverCarter0972
I'm reviewing old gusseted-bracket records for our proposed FR10 cell. Alignment under restraint looks good; released dimensions don't meet the drawing. Before we inherit the correction routine, how do I trace which result belongs to fit-up, location or final acceptance? Records only, no live welding changes here.

19 条回复

GA
GabrielChen1149

Can one identified bracket be followed all the way through those notes, rather than joining pages because they share a date?

6
AL
AlexBell0646

Keep the drawing revision beside it. Otherwise even matched measurements may answer different requirements.

16
HA
HanaBarnes0535

And preserve the measuring supports. A dimension recorded in restraint isn't interchangeable with a released inspection just because the feature name matches.

8
OL
OliverCarter0972

I can follow two assemblies by their traveller numbers. One has a released result, then a correction entry, then an accepted result. The other only has the accepted sheet.

2
CA
CallumBrooks0795

Then the first assembly gives you a documented sequence, not an uncorrected process result. The second leaves that sequence unknown. I would not combine them into an average for selecting the new fixture.

12
GA
GabrielChen1149

Does the correction entry say what was done, or is it just a signature beside the word?

13
AL
AlexBell0646

You could ask the operator who signed it, with the actual sheet in front of them.

13
HA
HanaBarnes0535

Alex, yes, but don't turn a remembered explanation into a missing measurement. It can describe the method without reconstructing the amount.

18
OL
OliverCarter0972

It is just a signature. The former operator has agreed to talk it through with fabrication and quality. I've marked the pre-correction measurement as available only for the first assembly.

22
AL
AlexBell0646

Hana, agreed. I meant identify the operation, not ask them to remember a number.

13
CA
CallumBrooks0795

Incoming fit-up is still absent from this discussion. Does either traveller show preparation before the assembly was loaded? A released failure may be real while its starting condition remains undocumented.

21
OL
OliverCarter0972

Only a general fit-up tick. No gaps or component measurements. That's another missing stage, and it affects both assemblies.

13
GA
GabrielChen1149

Did the operator meeting clarify what the tick actually covered?

13
OL
OliverCarter0972

Yes. They checked that the prepared pieces could be assembled, but sometimes dressing happened first. The correction signature referred to a separate post-release operation. Quality has now split those stages in the proposed study sheet.

17
AL
AlexBell0646

Thanks for reporting the preparation too. It would have been easy to omit that from the new handover.

18
HA
HanaBarnes0535

That still does not establish that dressing caused the later dimensional error. Keep it as a process dependency to investigate, not the explanation you've finally found.

10
CA
CallumBrooks0795

The useful outcome is that the new study can observe the stages separately. It needs agreed inspection methods as well as boxes for values, or different supports may create another set of incomparable records.

6
GA
GabrielChen1149

Who approves that study sheet before the cell specification uses it?

22
OL
OliverCarter0972

Fabrication and quality approved the recording plan today, including supports and drawing references. The old accepted figures are no longer being used as evidence of uncorrected output. We still need the new study before choosing the fixture scheme.

12