controller delivered to service, still no intake after 38 days

ClaraBrown0872 · 2026年8月20日 17:51 UTC

回复讨论
CL
ClaraBrown0872
Our FR10 sorting cell is still down while its controller is somewhere after delivery to the seller's service address in China. I sent it under their return agreement and kept the transport record. After 38 days they have not confirmed intake or inspection. Can I get the item located before discussing replacement costs?

10 条回复

OM
OmarArcher0404

Ask service to trace the controller by serial against the return agreement and delivery receipt. A parcel scan does not identify what their technician received.

13
MI
MiaChan1079

Include the packaging marks and delivery date in one message to the service manager. Ask them to distinguish receipt by their building from intake into assessment. Your planning problem is not yet a repair duration; it is an unaccounted-for component.

19
CL
ClaraBrown0872

Their warehouse found the parcel under our company name, but service still has no serial-linked intake. I've sent the original packing photos to both contacts.

13
SO
SofiaBaker0456

Can warehouse confirm the contents, not only the label on the box?

18
CL
ClaraBrown0872

They have confirmed the serial from the controller now. It was on a returns shelf, not in the inspection queue. Service says it has moved to intake.

25
OM
OmarArcher0404

Have they issued an assessment reference and a person responsible for it? Located is better, but still leaves the next action owner unclear.

19
MI
MiaChan1079

And preserve when each step happened. Otherwise the eventual summary may describe all this time as technical investigation, which would conceal the delay your workshop actually experienced.

1
CL
ClaraBrown0872

Assessment reference received with a named technician. Thanks, Omar; I can finally ask about a specific job instead of forwarding the delivery page again.

4
CL
ClaraBrown0872

The technician has issued findings and a proposed repair with a charge. I have asked for the repair scope and return checks before deciding; finding it did not settle who pays.

11
OM
OmarArcher0404

Keep approval and return-to-service separate as well; an agreed repair price would not establish the controller passed its checks or that your sorting setup is ready.