Who is responsible for ending the inspection request?

FelixAbbott0023 · 2025年4月16日 12:20 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

FE
FelixAbbott0023
Our FR10 training-cell application occasionally misses the PLC's short inspection request, and the two owners disagree about who should clear it if we hold it until acknowledged; what should we agree before they change this ordinary job handshake, which is separate from the engineered safety functions?

3 条回复

LE
LeoBrooks0797

Write down who writes each signal and what makes them set or clear it. Then walk one request through together, including a timeout. If both programs can clear the same request, you'll keep getting two explanations for one missed job

12分
FE
FelixAbbott0023

The joint walkthrough found both sides clearing the request under different assumptions; they have agreed single ownership and are reviewing reconnect behaviour before testing the revised interface.

19分
LE
LeoBrooks0797

Put the accepted-job identity in that review too. Holding a bit longer doesn't tell a restarted application whether it's looking at old work or a new request

9分