our coupon handover shows a routine without identifying its dependencies

PavelBaker0440 · 2026年2月20日 15:25 UTC

已关闭
PA
PavelBaker0440
The FR10 screenshots name the coupon routine but not its revision or the called checks. I have asked the integrator for the matching program set. How should I tie those files to the fixture assumptions in the handover?

2 条回复

SO
SofiaBrown0891

Use one checked inventory linking program revisions, called routines, fixture identity and expected ordinary PLC confirmations.

9
PA
PavelBaker0440

Integrator supplied the inventory but one called routine is still absent from the export. I've returned that specific gap. No point calling it a complete handover because the top-level screenshot matches.

-2