our coupon handover shows a routine without identifying its dependencies

PavelBaker0440 · 2026年2月20日 15:25 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

PA
PavelBaker0440
The FR10 screenshots name the coupon routine but not its revision or the called checks. I have asked the integrator for the matching program set. How should I tie those files to the fixture assumptions in the handover?

2 条回复

SO
SofiaBrown0891

Use one checked inventory linking program revisions, called routines, fixture identity and expected ordinary PLC confirmations.

9分
PA
PavelBaker0440

Integrator supplied the inventory but one called routine is still absent from the export. I've returned that specific gap. No point calling it a complete handover because the top-level screenshot matches.

-2分