Unpriced fixture work in the FR5 total

BethBaker0498 · 2025年5月7日 08:27 UTC

已关闭
BE
BethBaker0498
I cannot compare our FR5 packing proposals while one includes carton fixtures and the other puts them under customer scope with no price; how should that gap appear in the comparison?

4 条回复

DA
DanielChen1174

As unpriced work. Don't let an empty cell add up to a bargain.

9
BE
BethBaker0498

I have separated the priced subtotal from outstanding work and asked our toolroom for an estimate against the same carton range.

13
DA
DanielChen1174

Did they include changeover nests and staff time, or just the first fixture?

19
BE
BethBaker0498

Their estimate includes the agreed variants and design time; guarding and training still need comparable scope from the two suppliers.

21