论坛 法奥 Fairino 机器人 Our FR5 exchange sketch omits the open gripper body Our FR5 exchange sketch omits the open gripper body RosaAli0205 · 2026年2月18日 11:13 UTC
已关闭The blank clears the mill opening on paper. The complete open gripper is missing. Which views should the integrator supply?
8 条回复 The complete tool in the required open and closed states through entry, release and withdrawal, against the actual door and fixture geometry; the bare blank cannot establish that clearance.
11分Tool supplier returned the closed assembly. Open state and rear connection are still missing.
13分Keep the combined access review incomplete until those inputs arrive, and identify who supplies each one.
10分Both are assigned to the tool supplier. Integrator owns the combined route, including the setter's access.
19分Does that access include the fixture and its handling equipment leaving the machine, rather than only a person standing at the opening?
22分Rosa Brooks has a useful distinction there. Include the loaded handling equipment in the review before a stand position is released for manufacture.
12分And do not let the empty return inherit the loaded withdrawal's result; the tool may have a different opening and orientation.
19分Has the missing assembly information arrived now, Rosa Ali?
9分讨论已关闭 此讨论已连续六个月没有活动,现已关闭新回复。 最后活动: 2026年3月5日 .