ElliotBrown0944 · 2025年4月16日 20:24 UTC

已关闭
EL
ElliotBrown0944
I am reviewing an FR5 machine-loading proposal. The reach line ends at the aluminium blank in the fixture. The gripper body and open door are absent. I need the supplier to show usable access before we choose the arm. The same bay must remain accessible for manual setup.

13 条回复

LI
LiamBarnes0577

I have seen an apparently clear loading point fail on withdrawal. Ask for the loaded tool through the whole route, with the door at its actual open position.

0
EL
ElliotBrown0944

The supplier added the gripper and found that the proposed adapter passes close to the door edge. They have not checked the intermediate poses yet.

20
LI
LiamBarnes0577

Then clearance remains undecided. Include hoses and the held blank in that check; a clear view at the fixture alone is insufficient.

15
EL
ElliotBrown0944

They propose turning the base, which moves the elbow envelope towards the manual setup position. I have requested an updated combined layout.

23
LI
LiamBarnes0577

Have the machine users mark that setup space. I would not choose its limits from a plan view without seeing their tasks.

18
BE
BenAdams0109

Please include where the trolley goes. Ours lived in the only empty patch on the drawing, then the robot proposal claimed that patch too. Apparently the trolley was meant to float.

12
LI
LiamBarnes0577

That is exactly the sort of ordinary activity a machine-only model misses. Include routine supply, inspection and maintenance access in the layout review.

9
AN
AnnaBell0677

Who is paying for the extra layout work, and was a usable approach included in the original proposal?

10
EL
ElliotBrown0944

Access review was included. The supplier is revising its proposal under that scope. Operators have marked setup and trolley positions on the drawing.

14
AM
AmaraBarnes0600

Add the spare-tool change position while everyone is there; we discovered ours only existed if you moved a cabinet first, which was a pain for the person inheriting the job.

0
LI
LiamBarnes0577

Has the revised route been checked with the complete tool yet? The added human tasks help the layout, but that original question still needs an answer.

8
EL
ElliotBrown0944

The supplier's review supports a different base position with the proposed complete tool. Tool-change access is included. Final tool dimensions are still pending, so the arm choice remains conditional on that check.

23
LI
LiamBarnes0577

Carry that condition into the purchasing decision and assign the final review. A provisional envelope is useful for screening, provided nobody mistakes it for the delivered tool.