I've got packaging and tooling back onto the same FR10 layer revision. Now packaging accepts the support in the straight row but questions the turned row. Tooling calls the whole drawing accepted because its withdrawal space fits.
The project engineer has split those decisions on the review sheet. The turned row stays open and purchasing has the same status, not the supplier's single accepted stamp.