Who should own the missing spare cable after commissioning?

JaneChan1119 · 2025年3月3日 19:25 UTC

已关闭
JA
JaneChan1119
Our FR5 is here with its installed cable, but the separately promised spare kit is still outstanding. The seller says it will follow later. I am handing the project to maintenance and want that omission to survive the handover. How would you record it?

1 条回复

BE
BethBennett0759

I inherited one like this with the shortage buried in a former employee's inbox. Put the ordered spare items, received quantities, seller correspondence and named follow-up owner in the equipment handover record, with the kit explicitly outstanding.