The FR10 demo carton has none of our awkward surfaces

NadiaChan1074 · 2025年8月12日 09:12 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

NA
NadiaChan1074
I'm reviewing the carton pickup proposal. Supplier used a smooth empty box; ours arrive packed, with a broad printed panel on one source and a rougher finish on the other. Same outside dimensions. Apparently that made them the same test.

13 条回复

MI
MinaArcher0424

Ask for representative packed samples from both sources in the assessment. Did you observe a problem with your cartons, or has the supplier only shown the smooth empty one so far? That changes how I would describe the gap.

20分
NA
NadiaChan1074

Only their box has been tried. No failure on ours to report. I object to them calling the concept demonstrated for our packaging.

17分
MI
MinaArcher0424

Then describe the current demonstration narrowly and request the missing comparison. Include where the cups contact each carton, not just the packaging source name. It may be possible to use a different clear area.

22分
JO
JonasBrown0894

Add the operator's response to an unsuccessful pickup to the proposal, including any preparation time. Otherwise the trial can pass while your staffing estimate remains incomplete.

-4分
RO
RosaBrown0901

Send cartons taken from ordinary deliveries, Nadia. I nearly selected our nicest examples for a supplier once, which would have made their task easier and the answer less useful. Include the seam positions you actually see.

9分
NA
NadiaChan1074

We've gathered filled examples from both sources, including the rough board and the usual tape variation. Jonas, there's no failed-pick response in the offer. I've asked for that with the trial plan.

4分
OM
OmarChen1187

Will the supplier identify the cup set used? It would help whoever orders replacements if the eventual trial uses something different from the quoted set.

17分
MI
MinaArcher0424

Also watch release into the receiving position. I would not accept a hanging-carton photograph as the full comparison, even with your own filled carton in it.

15分
NA
NadiaChan1074

Omar, the revised plan identifies a different cup arrangement for each carton source. Mina, transfer and release are included. I'm less keen on a changeover every time purchasing changes source.

9分
JO
JonasBrown0894

Then price that changeover and ask purchasing how often the sources mix within an order. A workable pickup can still be an awkward production choice.

9分
RO
RosaBrown0901

Have they ruled out one arrangement for both, Nadia, or just proposed two? I would ask before you carry two sets of tooling and the identification work that comes with them.

9分
NA
NadiaChan1074

They haven't ruled it out. Purchasing says both sources can be on the same pallet, so I've asked for a common-tool comparison first. No tooling order placed.

12分
OM
OmarChen1187

Mixed on one pallet makes identification part of the job too, unless the common arrangement covers both. Worth including that in your handover discussion.

9分