Ask for the delivered assembly identity and a comparison against the confirmed fixture revision, treating the suffix and visible interface differences as observations rather than proof of either compatibility or incompatibility.
简体中文界面。帖子、指南及政策正文保留原文;未对原文作自动翻译。
My delivered FR5 adapter interface still lacks a drawing-based comparison
ReeceAdams0123 · 2026年8月19日 20:37 UTC
17 条回复
Keep the installation hold visible to whoever schedules the work. A delivery and a reassuring seller message can become a fitting date very quickly, especially when the missing comparison lives in somebody else's email.
10分Have tooling identify the actual locating and mating features on that comparison, because a general robot description won't answer whether your fixture meets the delivered adapter as intended
19分Hold is recorded. Toolmaker marked the shoulder and locating face differences; seller has those beside the confirmed drawing.
9分Can the seller supply the as-delivered adapter drawing before anybody proposes remachining your tooling, so the comparison starts with identified geometry rather than an expensive trial fit?
10分Who owns the combined decision if the robot package and your fixture came from different people? Both could reply within their own scope and leave you with nobody accepting the assembled arrangement.
9分Include the program and setup assumptions that depend on the interface too. A changed stand-off can reach beyond whether two faces mate, so a purely mechanical comparison may not cover every affected part of the handover.
-6分Reece, is the apparent stand-off change measured yet? Omar is right to raise dependencies, but I would label the geometry difference as observed until the drawing or measurement establishes its size.
18分Not measured yet. Integrator owns the combined review. I've requested the delivered drawing; no remachining agreed.
25分Keep the observations and confirmed dimensions in separate columns when it arrives, so the technical review can see exactly which uncertainty the new document answers.
12分Delivered drawing received. Shoulder differs from the confirmed assembly; toolmaker found it conflicts with our existing locating recess.
10分That gives the fixture review an identified mismatch; ask for the agreed adapter as one option before assuming your existing tooling must absorb the change
3分And price responsibility, not only geometry. Supply of the agreed part and a redesign proposal have different work, timing and acceptance questions. No reason for you to choose the second by default.
0分Does the proposed resolution include updating the handover, or would the next maintainer still receive the drawing you originally ordered against?
15分Seller offers the agreed adapter, availability unconfirmed. Integrator will review its complete arrangement when identified; original delivered interface remains unaccepted.
2分Thanks for coming back with the mismatch, Reece. Keep the offer separate from receipt and acceptance; it answers which route the seller proposes, not when your tooling can be fitted.
14分Once that part is available, the integrator can close the affected setup and program assumptions against its identified assembly. The suffix question should remain a separate record if it still lacks an explanation.