The robot quote was only half our packing estimate

AdamBailey · 2025年4月27日 23:53 UTC

已关闭
AD
AdamBailey
Our FR10 packing estimate grew once fixtures, guarding and training appeared. I'm comparing two proposals, but several lines still say by customer. How should I show those without guessing a tidy total?

20 条回复

AA
AaronCarter0958
回复 AdamBailey

Don't make them zero. Who is the customer person expected to do each bit? If nobody can answer that, you haven't got an estimate for it yet.

19
AD
AdamBailey

That's what happened in my spreadsheet. Empty price cells summed as zero, and the cheaper proposal had more of them.

6
AA
AaronCarter0958
回复 AdamBailey

Classic bargain. All the work is elsewhere.

16
AD
AdamBailey

I've changed those to unpriced with an owner column. The overall comparison now says incomplete. Less satisfying, more accurate.

1
AA
AaronCarter0958
回复 AdamBailey

Get a price range where someone has enough information to give one, and say what it's based on. Don't invent a range just to fill the coloured cell either.

9
JO
JoBarnes0592
回复 AdamBailey

Does by customer include your time commissioning it, or just buying the missing kit?

12
AD
AdamBailey

Both, depending on the line. One supplier expects us to teach the product variants. I hadn't included staff time for that.

13
AA
AaronCarter0958
回复 AdamBailey

Ask them which variants and what support they provide. Teaching one prepared sample and owning every changeover afterwards are rather different jobs.

25
LU
LuisAdams0173
回复 AdamBailey

Our fixture quote looked decent until I asked who was making the spare nests. Me, apparently. In the time left over from all the other things I was supposedly doing for free.

1
AA
AaronCarter0958

Toolroom time is an actual cost. Amazing how often the spreadsheet disagrees.

21
GR
GraceAllen0320

List spare nests and wear parts by quantity. A vague spares allowance won't tell stores what should arrive.

12
AA
AaronCarter0958
回复 AdamBailey

What have the two quotes actually included for training? Hours, people, subjects? It's another word that can cover anything from a proper handover to someone pointing at start.

8
AD
AdamBailey

One says a day on site. The other lists operator and maintenance sessions but no duration. I've asked both for the content, attendees and follow-up support.

12
JO
JoBarnes0592
回复 AdamBailey

And who covers the attendees' normal jobs while they're learning?

16
AD
AdamBailey

Added staff cover. We now have estimates for internal fixture work and a list of questions on training. Still waiting for a complete guarding proposal.

12
AA
AaronCarter0958
回复 AdamBailey

That last one could change the layout, so avoid treating it as a bolt-on price. Have whoever owns the cell design settle how it's meant to work with loading and access.

8
LU
LuisAdams0173

And cleaning. We had to get a trolley through a gap the first drawing filled with a cabinet, which was a pain to discover after everyone liked the layout.

10
GR
GraceAllen0320

Use the same layout revision for both revised quotes. Otherwise a low price may just be for the older, smaller job.

4
AA
AaronCarter0958
回复 AdamBailey

Are you getting somewhere with it now, or still collecting exclusions?

7
AD
AdamBailey

Somewhere, finally. We can compare the priced items and see exactly what remains open. I haven't ranked the totals yet; the two suppliers are now quoting the same training and layout scope.

17