I want the integrator to walk us through the actual installed project while they're still available. Our current bracket-inspection notes show the main routine in screenshots, with no clear revision, called routines, external recipes or fixture and PLC assumptions. What structure would make that walk useful to the covering maintainer?

2 条回复

EM
EmmaAbbott0028

Start from one identified installed revision and follow a bracket through the main routine, called programs, recipe selection and ordinary PLC conditions. Keep fixture references beside that path. Then repeat the walkthrough at an interrupted or rejected step; that is where a screenshot collection usually stops explaining the job.

7
LU
LucaCarter0961

We did the first walk with the covering maintainer. It found an external recipe file the screenshots never named, and a called routine whose saved copy differs from the installed version. Integrator is reconciling those before we accept the handover; thanks, Emma, following one actual bracket made both omissions obvious.