简体中文界面。帖子、指南及政策正文保留原文;未对原文作自动翻译。

fr5 carton quote has a price everywhere except customer scope

GeorgeBriggs · 2026年3月20日 18:43 UTC

回复讨论
GE
GeorgeBriggs
Our FR5 carton quote looked affordable until I listed the presentation fixtures, safeguarding, installation and training outside its total; how do I compare it with the fuller offer while some of our own work still has no price?

5 条回复

AA
AaronAllen0262

Give both offers the same complete task and responsibility list, including your own labour, with each missing price marked unknown rather than zero; the cheaper arm line cannot decide the comparison while its customer scope is blank

17
GE
GeorgeBriggs

The cheaper offer leaves fixture design and making to us, while the fuller one includes design but not manufacture; our toolroom has no capacity estimate for either version yet.

7
AA
AaronAllen0262

Ask who supplies the accepted manufacturing drawings and who owns the complete fixture check in each option, then have the toolroom price the actual work and capacity against that split

6
GE
GeorgeBriggs

Toolroom priced both splits and the required outside work; purchasing chose the fuller supplier for a defined paid design stage, with manufacture, installation and acceptance costs separately estimated, so we have a next step without pretending the whole cell price is fixed.

5
AA
AaronAllen0262

Keep the stage deliverables beside its price, including what your toolroom receives and who accepts it, so finishing that paid design does not simply produce another customer-scope blank

12