The bracket gauge appears only after straightening

MayaChan1084 · 2025年11月19日 20:59 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

MA
MayaChan1084
I've found our old FR10 bracket route sheet. The gauge check comes after bench straightening. Can its pass marks tell the fixture designer anything about the bracket just after release?

13 条回复

WI
WillBarnes0574

They describe the final checked condition, not the untouched released one. Are any earlier readings preserved against individual brackets?

4分
MA
MayaChan1084

Only one rejected bracket has an earlier reading. It was kept because the customer queried it.

17分
JA
JackAllen0341

Our review nearly started from samples of the wrong revision. What drawing belongs to that retained bracket, and is it the one the new fixture is meant to handle?

11分
AD
AdaAllen0303

Also establish what the old gauge measures before reusing it. We had two unidentified blocks offered as a measurement method, which was optimistic even by workshop standards.

9分
WI
WillBarnes0574

Ada's gauge question and Jack's revision question can be checked without a new trial. The missing released history may still require current-part observations afterwards.

15分
MA
MayaChan1084

The retained bracket is revision G, same as our proposal. The gauge has no reference marking. Quality is comparing its contact arrangement with the drawing.

7分
CA
CalebAli0232

Same revision helps. One queried bracket still cannot supply a correction rate.

13分
MA
MayaChan1084

Understood. I have kept it as an example, not a percentage. The new observation sheet separates released reading, correction and final reading for each part.

8分
JA
JackAllen0341

Does someone record the correction work as it happens? Final measurements won't tell the estimator how much active work or waiting sat between the two checks.

7分
AD
AdaAllen0303

And try the sheet with the operator. We found an entry that both people assumed the other would fill in, which would have produced another beautifully empty column.

9分
MA
MayaChan1084

Operator and inspector have tried the draft together. The operator owns correction entries; inspection records both measurements. Quality has not approved the old gauge, so the current check will use its defined method instead.

1分
MA
MayaChan1084

The first observation batch is complete. Individual parts stayed identified, including the ones corrected. The estimator is reviewing the work entries with fabrication before changing the allowance.

8分
WI
WillBarnes0574

Did the ordinary batch resemble the retained reject, Maya, or did that example turn out to be unusual?

7分

讨论已关闭

此讨论已连续六个月没有活动,现已关闭新回复。 最后活动: .