Our vacuum-tool report confirms a seal on one flexible stainless cover panel. We receive a stack. I have already learned to count manual preparation on another trial, so this time I want the panel separation and any support during transfer included before calling the handling concept complete.

2 条回复

AL
AlexAbbott0037

Ask for the intended stack-to-fixture sequence, including how a second panel or failed separation is detected and handled. Somebody must own those cases, not leave them to the person beside the cell.

8
CA
CallumBrooks0795

The supplier has agreed to review representative stacks and the support arrangement, but has not proposed the single-panel confirmation yet. I have kept that as an explicit gap rather than letting the seal report answer it.

17