My FR10 estimate priced the arm and forgot the people

ElenaAllen0340 · 2025年7月23日 01:08 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

EL
ElenaAllen0340
I need to revise our spacer-loading proposal before asking my colleague to support it. I priced the FR10 and gripper but left fixture development, operator preparation and cover training vague. What should a small pilot measure to give us a fair decision on the complete job?

4 条回复

CH
ChloeBrooks0831

Have you observed one normal manual order from incoming parts through clearing the station?

19分
EL
ElenaAllen0340

Only the loading step. The operator also sorts the spacers and changes the nest, which I treated as existing work without checking whether the proposal adds more of it.

3分
CH
ChloeBrooks0831

Use the same starting condition for both comparisons, including preparation, changeover and clearing. Record who does each.

6分
EL
ElenaAllen0340

My colleague and the operator helped map that sequence. The pilot now includes representative parts, fixture cost, preparation and cover training. We still need the supplier's revised scope before setting a budget.

17分

讨论已关闭

此讨论已连续六个月没有活动,现已关闭新回复。 最后活动: .