My FR10 estimate priced the arm and forgot the people

ElenaAllen0340 · 23 Jul 2025, 01:08 UTC

Closed
EL
ElenaAllen0340
I need to revise our spacer-loading proposal before asking my colleague to support it. I priced the FR10 and gripper but left fixture development, operator preparation and cover training vague. What should a small pilot measure to give us a fair decision on the complete job?

4 replies

CH
ChloeBrooks0831
Replying to ElenaAllen0340

Have you observed one normal manual order from incoming parts through clearing the station?

19 points
EL
ElenaAllen0340
Replying to ChloeBrooks0831

Only the loading step. The operator also sorts the spacers and changes the nest, which I treated as existing work without checking whether the proposal adds more of it.

3 points
CH
ChloeBrooks0831
Replying to ElenaAllen0340

Use the same starting condition for both comparisons, including preparation, changeover and clearing. Record who does each.

6 points
EL
ElenaAllen0340
Replying to ChloeBrooks0831

My colleague and the operator helped map that sequence. The pilot now includes representative parts, fixture cost, preparation and cover training. We still need the supplier's revised scope before setting a budget.

17 points