I cannot use our FR5 monitor total for planning yet. Reconnecting adds the retained plate completion again, even though the saved job register still identifies the same check. The operator did not request another run.

3 条回复

AN
AnikaBennett0769

Ask the application owner how it matches a completion to the saved job before increasing the total; reconnecting should not invent a second physical plate

4分
HA
HarishAbbott0054

They found an unconditional increment on the first successful read after reconnect. The retained job reference is available, but that callback did not use it. A bookkeeping revision is being tested.

8分
AN
AnikaBennett0769

Try an unknown reference too, so the revision has somewhere honest to put a completion it cannot match rather than guessing it into the shift figure