Which released-bracket check belongs in this FR10 quote?

LiamChen1186 · 2025年9月1日 04:54 UTC

已关闭
LI
LiamChen1186
Separate FR10 bracket quote this time. Supplier includes an in-fixture check, but our old final acceptance followed correction. Which inspection step should I ask them to price?

11 条回复

AD
AdaBrown0912

Ask quality for the released-part instruction first. Price the check you actually need.

11
LI
LiamChen1186

Quality sent Q8. It checks the base and upright after the correction operation.

9
AD
AdaBrown0912

Send Q8 with the route, then. The supplier needs to see where that check sits.

13
DA
DanielAbbott0043

I'd ask for the correction decision too, not just the final measuring time. We have a habit of pricing the tidy inspection bench and forgetting the person who sorts which parts go to the less tidy one.

-2
LI
LiamChen1186

That decision isn't in Q8. Fabrication has been asked for its earlier check.

14
EL
EllaArcher0381

Does the quote assume the new fixture removes correction altogether? I would want that stated openly if it explains the missing step.

12
LI
LiamChen1186

Yes, Ella. Supplier expects no correction, but hasn't shown a trial on our current bracket.

9
NI
NinaBrown0936

I've watched that expectation turn into an operator with a hammer beside a supposedly finished cell. Ask for a trial result before removing the work. And don't let the old correction method become the new default without review either.

16
DA
DanielAbbott0043

Nina, did they ever put the extra work into the cycle figures, or leave it outside the number?

25
NI
NinaBrown0936

They eventually counted it. The first report timed only the robot and looked fantastic. Full-shift output was rather less impressed.

17
LI
LiamChen1186

I've requested Q8 inspection pricing and a current-part trial before accepting the no-correction assumption. Fabrication's selection check still outstanding.

15