Which released-bracket check belongs in this FR10 quote?

LiamChen1186 · 1 Sept 2025, 04:54 UTC

Closed
LI
LiamChen1186
Separate FR10 bracket quote this time. Supplier includes an in-fixture check, but our old final acceptance followed correction. Which inspection step should I ask them to price?

11 replies

AD
AdaBrown0912
Replying to LiamChen1186

Ask quality for the released-part instruction first. Price the check you actually need.

11 points
LI
LiamChen1186
Replying to AdaBrown0912

Quality sent Q8. It checks the base and upright after the correction operation.

9 points
AD
AdaBrown0912
Replying to LiamChen1186

Send Q8 with the route, then. The supplier needs to see where that check sits.

13 points
DA
DanielAbbott0043
Replying to LiamChen1186

I'd ask for the correction decision too, not just the final measuring time. We have a habit of pricing the tidy inspection bench and forgetting the person who sorts which parts go to the less tidy one.

-2 points
LI
LiamChen1186
Replying to DanielAbbott0043

That decision isn't in Q8. Fabrication has been asked for its earlier check.

14 points
EL
EllaArcher0381
Replying to LiamChen1186

Does the quote assume the new fixture removes correction altogether? I would want that stated openly if it explains the missing step.

12 points
LI
LiamChen1186
Replying to EllaArcher0381

Yes, Ella. Supplier expects no correction, but hasn't shown a trial on our current bracket.

9 points
NI
NinaBrown0936
Replying to LiamChen1186

I've watched that expectation turn into an operator with a hammer beside a supposedly finished cell. Ask for a trial result before removing the work. And don't let the old correction method become the new default without review either.

16 points
DA
DanielAbbott0043
Replying to NinaBrown0936

Nina, did they ever put the extra work into the cycle figures, or leave it outside the number?

25 points
NI
NinaBrown0936
Replying to DanielAbbott0043

They eventually counted it. The first report timed only the robot and looked fantastic. Full-shift output was rather less impressed.

17 points
LI
LiamChen1186
Replying to NinaBrown0936

I've requested Q8 inspection pricing and a current-part trial before accepting the no-correction assumption. Fabrication's selection check still outstanding.

15 points