Can I compare FR5 positions before the gripper outline arrives?

JonasBennett0720 · 2026年3月7日 16:44 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

JO
JonasBennett0720
Our supplier wants a preferred FR5 position for removing aluminium blanks. The sketch reaches the fixture but omits the complete gripper and open door. I can mark the machine access we need, but I cannot see how to choose between two tool-free drawings without guessing.

14 条回复

OL
OliverBrooks0798

Have they said what tool information they need before comparing the positions, Jonas, or are they treating that as work after selection?

9分
JO
JonasBennett0720

Work after selection. Toolmaker has a candidate assembly, but its outline has not reached the layout person.

9分
JA
JaneBrown0945

Get those two talking. There is already a candidate to draw, so this isn't a philosophical argument about designing the tool before choosing the arm.

7分
MA
MayaParts

You could buy a bounded access study next rather than a stand, if the supplier needs payment for the combined comparison.

-1分
JO
JonasBennett0720

They have agreed a combined study and received the candidate tool outline. The first position puts its rear fitting into the door area. The second needs more space beside the machine.

5分
TH
ThomasChan1060

What currently occupies that extra space?

6分
JO
JonasBennett0720

Fixture trolley waiting position. The setter will not lose it without another usable place.

2分
OL
OliverBrooks0798

Could the receiving layout change to release that place, or would it simply move the obstruction to the next task?

13分
JA
JaneBrown0945

Try it on the floor plan with the setter before writing 'trolley elsewhere'. Elsewhere is where every inconvenient thing goes to disappear from a quote.

14分
MA
MayaParts

And if it needs a layout change, include that in the second option's price rather than treating it as customer preparation nobody costs.

14分
JO
JonasBennett0720

The setter identified an alternative trolley position, but it shares the route used to replenish the receiving trays. We are comparing the actual exchanges, not assuming both can occupy it together.

17分
TH
ThomasChan1060

Who does both exchanges on the ordinary shift?

3分
JO
JonasBennett0720

Usually the same operator. Their walkthrough found the tray replenishment would have to stop during fixture exchange. They can live with that for our batches, and planning is costing the interruption.

15分
MA
MayaParts

Then you have a defined tradeoff to price. The first position is rejected; the second still has tool-access and operating costs to settle before purchase.

2分