How do I compare FR10 quotes when 'customer supplied' keeps growing?

RebeccaCarter1039 · 2026年2月4日 03:05 UTC

已关闭
RE
RebeccaCarter1039
The arm price is firm, apparently because all the uncertain bits have been put in our column. Presentation fixtures, guarding design, training and even who gets the boxed kits into the first nest. How do I compare the complete proposals without inventing prices for work nobody has scoped?

11 条回复

AM
AmaraArcher0426

Which missing item could change the layout? Start there, before filling the spreadsheet with allowances.

16
RE
RebeccaCarter1039

Presentation. One supplier assumes aligned boxes delivered individually; the other includes a tray but says we prepare it. Neither owns getting our actual packed kits into that condition.

18
HA
HazelAdams0136

Define that incoming work with the operator and both suppliers. You can list an unknown cost honestly, but not compare two totals that start at different points in the job.

10
RE
RebeccaCarter1039

We described the real starting condition and sent both the same order sequence. Operator preparation is explicit now. I have blank costs labelled awaiting scope, rather than zeroes that make the totals look wonderfully close.

4
JA
JackBennett0776

Who is responsible for the complete safeguarding design in each proposal?

14
CA
CalebBrown0928

And what does training cover? Selecting a prepared job is a smaller handover than changeover, ordinary stops and defined recovery. The person covering the next shift needs more than a demonstration attendance line.

13
RE
RebeccaCarter1039

Jack, both name the integrator for safeguarding, but the layouts need the presentation decision first. Caleb, one training line only covers normal operation. I've asked for changeover and recovery scope with the same staffing assumptions.

2
AM
AmaraArcher0426

Has either supplier priced the common starting condition yet?

13
RE
RebeccaCarter1039

One has revised its scope and price. The other still excludes sorting the incoming boxes. We can compare that exclusion plainly now, but I'm not declaring the second offer cheaper because its total omits the job.

0
HA
HazelAdams0136

Could you price that preparation separately with a defined owner, Rebecca? It may still be a viable option; the exclusion needs a real cost and staffing answer, not automatic rejection.

5
CA
CalebBrown0928

When those scopes settle, ask who supports a failed changeover after handover. That is another service people often assume belongs to whichever supplier answered the phone during the demonstration.

19