How do I compare FR10 quotes when 'customer supplied' keeps growing?

RebeccaCarter1039 · 4 Feb 2026, 03:05 UTC

Closed
RE
RebeccaCarter1039
The arm price is firm, apparently because all the uncertain bits have been put in our column. Presentation fixtures, guarding design, training and even who gets the boxed kits into the first nest. How do I compare the complete proposals without inventing prices for work nobody has scoped?

11 replies

AM
AmaraArcher0426
Replying to RebeccaCarter1039

Which missing item could change the layout? Start there, before filling the spreadsheet with allowances.

16 points
RE
RebeccaCarter1039
Replying to AmaraArcher0426

Presentation. One supplier assumes aligned boxes delivered individually; the other includes a tray but says we prepare it. Neither owns getting our actual packed kits into that condition.

18 points
HA
HazelAdams0136
Replying to RebeccaCarter1039

Define that incoming work with the operator and both suppliers. You can list an unknown cost honestly, but not compare two totals that start at different points in the job.

10 points
RE
RebeccaCarter1039
Replying to HazelAdams0136

We described the real starting condition and sent both the same order sequence. Operator preparation is explicit now. I have blank costs labelled awaiting scope, rather than zeroes that make the totals look wonderfully close.

4 points
JA
JackBennett0776
Replying to RebeccaCarter1039

Who is responsible for the complete safeguarding design in each proposal?

14 points
CA
CalebBrown0928
Replying to RebeccaCarter1039

And what does training cover? Selecting a prepared job is a smaller handover than changeover, ordinary stops and defined recovery. The person covering the next shift needs more than a demonstration attendance line.

13 points
RE
RebeccaCarter1039
Replying to CalebBrown0928

Jack, both name the integrator for safeguarding, but the layouts need the presentation decision first. Caleb, one training line only covers normal operation. I've asked for changeover and recovery scope with the same staffing assumptions.

2 points
AM
AmaraArcher0426
Replying to RebeccaCarter1039

Has either supplier priced the common starting condition yet?

13 points
RE
RebeccaCarter1039
Replying to AmaraArcher0426

One has revised its scope and price. The other still excludes sorting the incoming boxes. We can compare that exclusion plainly now, but I'm not declaring the second offer cheaper because its total omits the job.

0 points
HA
HazelAdams0136
Replying to RebeccaCarter1039

Could you price that preparation separately with a defined owner, Rebecca? It may still be a viable option; the exclusion needs a real cost and staffing answer, not automatic rejection.

5 points
CA
CalebBrown0928
Replying to RebeccaCarter1039

When those scopes settle, ask who supports a failed changeover after handover. That is another service people often assume belongs to whichever supplier answered the phone during the demonstration.

19 points

Discussion closed

This discussion is closed to new replies after six months without activity. Last activity: .