our fr5 seal report starts with the panel already separated

HanaChen1144 · 2025年12月14日 21:35 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

HA
HanaChen1144
The FR5 tool supplier has shown a seal on one access panel, but our panels arrive stacked and the drawing has no support away from the cups. I want the proposal to cover getting one panel into the nest, not just holding whichever panel somebody kindly hands it

6 条回复

DA
DavidBarnes0606

Ask for the complete proposed sequence from the received stack to release in the nest, with support and single-panel confirmation explained; the seal report can stay as evidence for that one limited check

9分
HA
HanaChen1144

They've proposed manual separation as one option and a separate feeding arrangement as another. Neither includes the receiving support yet, which seems a fairly large common omission

22分
LI
LiamAbbott0055

Have the nest designer join that part of the review. The two feeding options may differ, but both still have to deliver a panel the nest can receive without someone straightening it by hand

18分
HA
HanaChen1144

Nest designer has asked for the actual held-panel shape and release sequence. We've kept the two preparation options separate for costing and left the transfer assessment open

12分
DA
DavidBarnes0606

Include your operator's preparation and refill work in the manual option, so it does not win by leaving the person outside the quoted system

22分
LI
LiamAbbott0055

Has the tool supplier answered the held-shape question since, Hana? That answer could change either option before you spend more time comparing their prices

10分