our fr10 packing comparison has too many free blanks

BenBench · 2025年12月7日 03:03 UTC

已关闭

主帖中文翻译暂不可用,以下显示英文原文;回复保留原文。 查看英文原文

BE
BenBench
I've put two FR10 packing proposals beside each other. One leaves the presentation fixture unpriced. The other omits operator training. Both totals look better than the complete job will cost

2 条回复

DI
DineshChen1169
回复 BenBench

Give both suppliers the same scope lines and mark unpriced work explicitly. Do the offers also assume the same person prepares the boxed kits and clears the finished trays?

12分
BE
BenBench

No. One assumes our packer prepares everything. I've added that work and asked both suppliers to state their staffing assumptions before comparing totals again

7分