Find the inspection instruction for both checks first. If they used different references, the two results may not describe the same feature in the same way.
简体中文界面。帖子、指南及政策正文保留原文;未对原文作自动翻译。
the old jig has a correction nobody owns
MayaAbbott0040 · 2025年5月29日 12:12 UTC
20 条回复
Clamped check has a sketch. Loose check just says height OK. Or not OK, depending on the sheet.
4分Can the inspector identify the loose-part setup? A photograph of the old checking kit might help them remember which tool they used.
14分Are the retained brackets actually the same revision?
14分Two revisions. Separated now.
4分Found the checking plate behind another jig. Sent photos to the retired inspector. No lifting party required, thankfully.
17分Has the inspector recognised it?
6分We once found a stop adjustment belonged to an incoming-part change nobody had told tooling about. Have you compared the component drawings as well as the finished bracket number?
21分Who is meant to explain this correction to the operators once the new cell is built?
9分That person should join the review. Even if the old correction is abandoned, they'll need to know what the new checks mean and who decides on a failed part.
12分Production lead. She's joined it. Inspector says the plate was for fit-up, not finished height. Different kit for that, still looking.
16分Any drawing for the extra stop itself?
5分No. Only the word correction and two pencil arrows. Doesn't even say which direction the adjustment went.
21分Then keep it out of the new fixture specification until its purpose is established. Quality can define the current acceptance check without inheriting those arrows.
7分Done. Current bracket requirements going back to quality and tooling. The copied stop is off the draft.
5分What did the component comparison show? Still wondering if the change explains why someone wanted that extra stop.
13分And has production got a clear owner for rejected brackets now?
5分Keep the old unknowns in the background notes, so nobody helpfully restores the stop later because the old jig had one.
7分Gusset changed, but no proof connecting it to the stop. Quality owns rejection decisions. Both points are on the review sheet; final measurements still pending.
8分I would be interested in those measurements when they arrive. At least the parts and checks now have clear identities.